Houston's driveway permit
When a driveway, curb or culvert job in Houston needs a city permit, the widths and spacing the city's design manual sets, who applies, and how plan review and inspections work.
On this page: 6 sections
A home's driveway in Houston is permitted through the Houston Permitting Center as the Residential Driveway, Sidewalk, or Curb & Gutter Permit (HPWOCE1011), under chapter 40 of the city's Code of Ordinances.1
When you need a permit
The residential permit covers building a new driveway or sidewalk, removing and replacing an existing driveway, sidewalk or curb and gutter, and extending a driveway.1 The commercial version, HPWOCE1012, needs a bond and may need Urban Forestry approval first.2
A driveway onto a freeway, highway, frontage road, tollway or farm-to-market road isn't the city's to permit. It needs approval from the agency that runs that road.3
Driveway standards
The city's Infrastructure Design Manual sets the rules, and its 2026 edition took effect on March 2, 2026.4 A driveway for a single-family house or a duplex is a Type A driveway.5
| Type A driveway | Minimum | Maximum |
|---|---|---|
| Two-way width | 10 feet | 24 feet |
| One-way width | 10 feet | 12 feet |
| Radius of the curved edge at the street | 4 feet | 10 feet |
A joint access driveway serving two lots must be at least 12 feet wide.6 On a narrow lot with its own driveway, 12 feet is the most allowed.7
For a Type A driveway, the manual sets these minimum distances:8
- 20 feet from an adjacent street's right-of-way;
- 20 feet between two driveways on the same property, or 10 feet between a pair of one-way driveways;
- 4 feet from the side property line.
A property can have at most two driveways, unless chapter 42 of the city code says otherwise, and the radius can't reach past the property line or into the street's or another driveway's curb radius.8 No driveway is allowed within the limits of an intersection, and a Type A driveway has to stay straight, the same width and unobstructed from the roadway to the property line.7 A driveway can't be built onto a local street where there's less than 20 feet of clear depth between the right-of-way and any obstruction.9
On a street with open ditches, every driveway crossing gets a culvert at least 24 inches across inside,10 and never narrower than the nearest culvert upstream.9 PVC isn't allowed for driveway culverts. High density polyethylene is allowed for single-family culverts only, and polypropylene and reinforced concrete are allowed too.11
Who applies
The application, form CE1023, is filed by the owner or the contractor. It asks for the project number, each driveway's width and length, the surface material, the cost of the work and a sidewalk, driveway, curb and gutter bond number. Whoever signs it certifies having a contract to do the work.9
How to apply
For the residential permit you need the application with a project number, two dimensioned site plans and a copy of the survey. Plan review is required. Plans go in through ProjectDox, or in person on Tuesday, Thursday and Friday from 8am to 4pm. The page lists a processing time of 1 business day. The permit is valid for one year, and any change to it needs a revision.1
Inspections
Before you book an inspection you need the permit and the traffic-approved stamped plans, the fee paid and the bond current. The culvert must be in and the driveway and sidewalk fully formed. The work is inspected before and after the concrete is poured, and it has to match the approved traffic-stamped site plan. Book through the city's online permits site or at 832.394.9496. Inspections are for the next business day, with no same-day slots, and repeated failures bring a re-inspection fee plus an administrative fee.1
Fees
The permit fee is set in the City of Houston fee schedule, under Building Code - Traffic. The Permit Office, which handles payment and bonds, is at 832.394.8899 or 832.394.9494.1
Houston Permitting Center, Houston Public Works and the City of Houston Infrastructure Design Manual, checked October 2026.
Sources (11)
- Houston Permitting Center: residential driveway, sidewalk, or curb & gutter permit, read October 23, 2026 ↑
- Houston Permitting Center: commercial driveway, sidewalk, or curb & gutter permit, read October 23, 2026 ↑
- City of Houston Infrastructure Design Manual 2026, section 15.1.03.N, read October 23, 2026 ↑
- Houston Public Works: 2023-2026 review cycle executive summary, read October 23, 2026 ↑
- City of Houston Infrastructure Design Manual 2026, section 15.2.07.C.1.j, read October 23, 2026 ↑
- City of Houston Infrastructure Design Manual 2026, Table 15.6, read October 23, 2026 ↑
- City of Houston Infrastructure Design Manual 2026, section 15.2.07.C.1.j, continued, read October 23, 2026 ↑
- City of Houston Infrastructure Design Manual 2026, Table 15.7, read October 23, 2026 ↑
- Houston Permitting Center: form CE1023, read October 23, 2026 ↑
- City of Houston Infrastructure Design Manual 2026, section 9.2.01.E.3, read October 23, 2026 ↑
- City of Houston Infrastructure Design Manual 2026, Table 9.3, read October 23, 2026 ↑